Published 2026-09-12 · Event 2026-05-12

Polar’s HER01 note is a Herøya site announcement, not a live Porsgrunn hall

An industrial interior with equipment carts and overhead pipework.
Photo Lawrence Krowdeed on Unsplash

On 12 May 2026 Polar Data Centers announced HER01 on Herøya Industrial Park in Porsgrunn, written as a 39,000-square-metre site ready for construction with an initial capacity in the region of 40 MW. A site announcement is not a commissioned hall.

Polar Data Centers’ 12 May 2026 Herøya note is the dated HER01 source used here. It announces an AI-ready data-center development on Herøya Industrial Park in Porsgrunn, about 130 kilometres from Oslo. A site announcement is not a commissioned hall.

The size sentence must stay a printed-design sentence. Polar writes a 39,000-square-metre site ready for construction and an initial capacity in the region of 40 MW, powered by renewable hydroelectric energy, with a targeted PUE of 1.12 and a Tier 3 design. Those are design figures. They are not a measured live load and not a named tenant list.

The readiness sentence must stay a readiness sentence. “Ready for construction” is a site-status claim. It is not a construction start on the ground and not first power.

Related grid notes stay on their own pages. Polar’s later DRA02 Drangedal announcement, Bitdeer’s Tydal lease and other Norwegian campus papers are different dates and different sites. This article does not import a Drangedal building or a Tydal contract into a Herøya announcement day. Polar Data Centers is not Polar Connect.

DataCenterSweden records 12 May 2026 as a Polar HER01 site announcement. No project identifier is attached. The next update would need a later primary source that names a construction start on the ground, a commissioned hall or a reserved offtake that is not only the printed region-of-40-MW sentence. Until then, HER01 stays an announced industrial-park site — not a live Porsgrunn hall.

Why it matters

A 40 MW Herøya headline on an industrial-park site is easy to file as live Telemark hall power. The May note is usable only if the announcement stays an announcement — not a commissioned hall.

What remains unknown

The note does not name a tenant, start construction on the ground or say the region-of-40-MW hall is already live.

Sources

  1. Polar announces a new AI-ready data-center development in Herøya, Norway Polar Data Centers, 2026-05-12. Checked 2026-09-12.