Helen Sähköverkko’s Helsinki 400 kV page is a DSO duty and tunnel plan, not reserved capital-region hall power

Utility transformers and a web of overhead power lines against a clear sky.
Photo Alivia Alva on Unsplash

Helen Sähköverkko’s Helsinki 400 kV page says an early-2026 Electricity Market Act change moved local and regional 400 kV development from the TSO connection toward the load onto the DSO. A duty shift is not reserved hall offtake and not a heat-reuse contract.

Helen Sähköverkko’s Helsinki 400 kV development page is the dated duty source used here. It says electricity use in Helsinki is growing quickly, driven especially by the clean transition as heating and transport electrify, while less electricity is produced locally. An early-2026 Electricity Market Act change means local and regional 400 kV networks now sit with the distribution-system operator. In Helsinki that means Helen Sähköverkko is responsible for developing the network from the main-grid connection point toward the load centres. A duty shift is not reserved offtake.

The tunnel sentence must stay a tunnel sentence. A new cable tunnel of about 4.2 kilometres is planned between Vanhakaupunki and Sörnäinen, because there is not enough room for 400 kV cables in today’s street structures. A new Sörnäinen 400/110 kV station is planned in the Hanasaari energy block. Tunnel construction is printed as starting in 2026, the Sörnäinen station in 2029, and the 400 kV connection in service in 2031. Those are programme dates. They are not a live Helsinki hall.

The forecast sentence must stay a city-forecast sentence. The page prints a Helsinki electricity-consumption forecast table and cites heating and transport electrification as drivers. Those figures are a city demand forecast. They are not a data-centre megawatt and not a heat-offtake contract. This article does not recast the table as reserved hall power.

Related grid notes stay on their own pages. Fingrid’s Länsisalmi–Vanhakaupunki 400 kV cable, Helen and OnZero’s Helsinki heat note and other capital-region papers are different dates and different instruments. This article does not import a TSO cable-build day or a signed heat volume into a DSO duty page.

DataCenterSweden records early 2026 as Helen Sähköverkko’s printed Electricity Market Act duty shift for Helsinki 400 kV. No project identifier is attached. The next update would need a later primary source that names a started 2026 tunnel, a commissioned 2031 connection or a reserved consumption agreement that this page does not print. Until then, the 4.2-kilometre tunnel stays a plan — not reserved Helsinki hall capacity.

Why it matters

A Helsinki 400 kV duty headline next to a TSO cable is easy to file as spare capital-region hall power. The page is usable only if the duty and the tunnel plan stay a duty and a plan — not a reservation.

What remains unknown

The page does not start the 2026 tunnel, commission the 2031 connection or name a reserved hall offtake or heat contract.

Sources

  1. Helsinki’s 400 kilovolt network — Helen Sähköverkko Helen Sähköverkko (publication date not stated). Checked 2026-09-12.