Published 2026-09-12 · Event 2026-08-19
Ellevio’s Dalarna snapshot is a regional-network timetable, not a Horndal or Falun cell

Ellevio’s Dalarna regional-network page, with a connection-case snapshot last updated on 19 August 2026, publishes a capacity timetable through about 2035. Larger connections must still be assessed one by one against the regional network and Svenska kraftnät. That page is not a data-center row and not spare power for Horndal, Falun, Borlänge or Smedjebacken.
Ellevio’s Dalarna capacity page is the dated regional-network source used here. The connection-case snapshot is last updated on 19 August 2026. The page itself is marked updated on 28 August 2026. Ellevio says local-network capacity is relatively good, while some regional-network bottlenecks sit against new industry. Every larger connection is assessed individually. A snapshot is not a reservation.
The timetable sentences must stay dated and split. In 2025–2026, connections up to 10 MW with downregulation can be handled in the existing network, case by case. In 2027 the Tandö transmission station is due in service and is said to enable about 250 MW of radially connected production; with new withdrawal customers, 100–200 MW of injection can be handled depending on type, place and flexibility. Around 2032 a further Svenska kraftnät 400 kV line between Bäsna and Repbäcken is said to enable 300–400 MW of production, again depending on type, place, flexibility and new withdrawal. Around 2035 the NordSyd Karlstad and Hallsberg legs appear: the Karlstad sentence names increased use and production across five counties and a customer-driven new station; the Hallsberg sentence names about 500 MW of further injection under the same conditions. Those are grid-build sentences. They are not a hall agreement.
The snapshot widget must not be copied into a Dalarna cell. Its caption on the fetched page names regional-network area Värmland/Närke, not Dalarna. This note therefore does not paste any megawatt cell from that table. Ellevio is a regional-network customer of Svenska kraftnät, so larger injection and withdrawal can also need a transmission application.
Named Swedish rows stay on their own papers. Google Horndal, EcoDataCenter Falun and Smedjebacken, the Borlänge Kvarnsveden planbesked and Ellevio’s Gävleborg snapshot are different issuers and sites. Svenska kraftnät’s county and bidding-area tables stay on their own dates. A Dalarna timetable does not become those files.
DataCenterSweden records 19 August 2026 as a Dalarna regional-network capacity snapshot. No project identifier is attached. The next update would need a later Ellevio snapshot whose table caption actually names Dalarna, or a property-level paper. Until then, 10 MW, 250 MW, 100–200 MW, 300–400 MW and about 500 MW stay timetable sentences — not reserved import for a named hall.
Why it matters
A Dalarna timetable next to Horndal and Falun is the easiest DSO picture to paste as spare county power. The August snapshot is usable only if 10 MW stays case-by-case and the Värmland/Närke widget stays uncopied.
What remains unknown
The Dalarna page does not publish a data-center row, does not name an applicant, and does not reserve import for a hall in this register.
Sources
- Grid capacity in Ellevio’s Dalarna regional network — Ellevio, 2026-08-19. Checked 2026-09-12.
- Connecting larger facilities to Ellevio’s regional network — Ellevio (publication date not stated). Checked 2026-09-12.