Published 2026-09-12 · Event 2026-03-20

Ei’s Örby–Högdalen remittal is a 220 kV underground filing, not reserved Stockholm hall power

Utility transformers and a web of overhead power lines against a clear sky.
Photo Alivia Alva on Unsplash

On 20 March 2026 the Energy Markets Inspectorate opened remittal of case 2025-104625, Ellevio’s 220 kV line between the Örby splice and Högdalen, with comments due 24 April. A remittal is not reserved Stockholm offtake.

The Energy Markets Inspectorate page for case 2025-104625, created 20 March 2026, is the dated remittal source used here. It says Ellevio AB has applied for a line concession for a 220 kV circuit (construction voltage 245 kV) between the Örby splice and Högdalen station in the City of Stockholm. The last day for comments is 24 April 2026. A remittal is not reserved offtake.

The rebuild sentence must stay a rebuild sentence. Ellevio’s project page says the existing 220 kV overhead line between Högdalen and Örby is to be replaced by an underground circuit about 3.5 kilometres long. The concession application was sent to the inspectorate on 19 December 2025. Written consultation under chapter 6 of the Environmental Code ran in February and March. Those are process facts. They are not reserved megawatts.

The street sentence must stay a street sentence. In Ellevio’s preferred alternative the trench sits mainly in the Örbyleden carriageway, with shorter stretches near cycle paths south of Stallarholmsvägen and north of Skönsmovägen. The northernmost part is likely to stay inside Ellevio’s station area. Open-trench times are written as relatively short because ducts are laid and the ground is backfilled. A preferred trench is not a commissioned cable.

Related grid notes stay on their own pages. Ellevio’s Akalla station note, the Värtan switchgear rebuild, the Skanstull in-service page and Stockholm’s Akalla 4:8 referral are different dates and different legal rows. This article does not import a named Stockholm hall or a city-committee referral into an Örby–Högdalen remittal day.

DataCenterSweden records 20 March 2026 as the Energy Markets Inspectorate remittal day for Örby–Högdalen. No project identifier is attached. The next update would need a later primary source that names a granted concession, a construction start or a reserved consumption agreement beside the 3.5-kilometre stretch. Until then, case 2025-104625 stays a remittal — not reserved Stockholm hall capacity.

Why it matters

A southern-Stockholm 220 kV underground headline is easy to file as spare hall power. The March remittal is usable only if the filing stays a filing — not a reservation.

What remains unknown

The remittal does not grant the concession, start construction or name a reserved consumption agreement beside Örby–Högdalen.

Sources

  1. Case 2025-104625 — 220 kV line between the Örby splice and Högdalen station Energimarknadsinspektionen, 2026-03-20. Checked 2026-09-12.
  2. New underground line between Högdalen and Örby Ellevio (publication date not stated). Checked 2026-09-12.